在新目标国家推出产品前不久,公司意识到该产品并不完全符合当地的数据隐私法。由于预算限制,公司管理层要求项目团队将可能的罚款成本与返工成本进行比较。返工的一部分包括向产品待办事项列表中添加新需求。在这种情况下,下面哪个选项最有可能帮助到你?
Shortly before rolling out a product in a newly targeted country, a company realizes that the product does not fully comply with local data privacy laws. Due to budget constraints, the company management asks the project team to compare costs for possible fines with costs for rework. Part of the rework would involve adding new requirements to the product backlog. In this situation, which of the following is most likely to help?


A.重构 Refactoring

B.用户画像 Personas

C.阶段关口 A phase gate

D.快速跟进 Fast tracking


知识点:PMP新模考(一)


参考答案:C


解析:知识点出处:PMBOK 6th   页码:P18 章节:1.2.4 阶段关口:为做出进入下个阶段、进行整改或结束项目集或项目的决定,做的阶段末审查。 审查一个阶段末的问题,做成本效益分析,以决定下个阶段的项目。