敏捷项目团队与产品负责人、项目经理和其他关键项目干系人会面,讨论项目必须经过的多层计划。参与者承认在发布和迭代级别上需要计划。项目经理指出,每天都需要规划。项目经理指的是以下哪项?
An agile project team meets with the product owner, project manager, and other key project stakeholders to discuss the multiple levels of planning that the project will have to go through. The participants acknowledge that planning will be required at the release and iteration level. The project manager indicates that planning will also be required on a day-to-day basis. Which of the following does the project manager refer to?
A.在项目中尽早实施体系结构刺探以降低技术风险 Carrying out an architectural spike to reduce technical risks as early as possible in the project
B.同步和协调导致完成任务的个别活动 Synchronizing and coordinating the individual activities that lead up to the completion of a task
C.获取项目团队成员,并根据资源管理计划分配任务 Acquiring project team members and assigning the tasks per the resource management plan
D.与组织中从事同一项目的其他团队协调团队活动 Coordinating team activities with other teams working on the same project in the organization
参考答案:B
解析:知识点出处:敏捷实践指南 页码:P53 章节:5.2.4 每日站会:·上次站会以来我都完成 了什么?·从现在到下一次站会,我计划完成什么?·我的障碍(或风险或 问题)是什么? 每日站会不解决问题。