项目管理专业人士资格认证(PMP)题库(1459题)


在编制人力资源计划时,项目经理发现来自职能部门的一名成员需要经过3天的培训,才能具备某种特定的技能,来完成某个特定的工作包。由于专业的限制,项目团队中没有其他人可以替代该成员。项目经理应该怎么做?
When preparing the HR plan, the project manager finds that a member from a functional department master a particular skill only after receiving three-day training to complete a specific work package. Due to limitation of profession, no other in the project team can replace this member. Then, what should the project manager do?


A.在项目进度计划中增加3天时间 To add extra 3 days in the project schedule

B.要求他利用业余时间完成这3天的培训 To request him to complete the 3-day training in his spare time

C.把该培训作为项目工作之一,加入项目计划中,并进行风险分析 To take the training as one of the project tasks, to participate in the project plan, and to perform risk analysis

D.要求用一个不需培训的成员来替换该成员 To require a member who doesn’t need to receive this training to replace the member


知识点:PMP新模考(一)


参考答案:C


解析:知识点出处:PMBOK 6th   页码:P342 章节:9.4.2.6 培训:如果项目团队成员缺乏必要的管理或技术技能,可以把对这种技能的培养作为项目工作的一部分。 项目经理按敏捷方式来,团队没有,说明团队没有掌握敏捷方法的技能。