一个项目是为了设计新的政府机构服务,其所有可交付成果均已获得验收。设计活动产生了许多机密文件。作为收尾过程的组成部分,项目经理应该做什么?
One project is designed to design new government agency services, and all of its deliverables have been accepted. The design activity produced a lot of confidential documents. What should project managers do as part of the closing process?
A.将文件添加到公司知识库以供将来参考 Add the document to the corporate knowledge base repository for future reference
B.参阅合同中有关处理机密材料的政策 Refer to the contract's policy on handing confidential material
C.从项目管理办公室(PMO)获得有关如何销毁机密材料的指示 Obtain instructions from the project management office(PMO)on how to destroy confidential material
D.按照PMO保留政策归档项目文件 Archive the project document per the PMO retention policy
参考答案:B
解析:知识点出处:PMBOK 6th 页码:P128 章节:4.7.3.4 组织过程资产更新:项目经理应该回顾以往的阶段文件,确认范围过程(见 5.5 节)所产生的客户验收文件,以及合同协议(如果有的话),以确保在达到全部项目要求之后才正式关闭项目。 机密文件的处理,需要审查合同中的要求,以确保正式关闭项目。