为了使新确定的干系人尽早参与项目,scrum master建议邀请他们参加即将举行的冲刺审查会议,以向干系人证明团队正在朝着正确的方向发展,并从干系人那里获得有关团队工作完成情况的反馈。以下哪个是邀请干系人参加本次会议的另一个原因?
To engage the newly identified stakeholders in the project at the earliest opportunity, the scrum master suggests inviting them to the upcoming sprint review meeting to demonstrate to the stakeholders that the team is moving in the right direction and get feedback from the stakeholders about what the team has accomplished. Which of the following is another reason for inviting the stakeholders to this meeting?


A.反思团队绩效 To reflect on the team performance

B.为下次冲刺确定高风险用户故事的优先级 To prioritize high-risk user stories for the next sprint

C.重新确定发布待办事项列表优先级 To reprioritize the release backlog

D.讨论下次冲刺的高级别计划 To discuss the high-level plans for the next sprint


知识点:PMP新模考(一)


参考答案:D


解析:知识点出处:敏捷实践指南 页码:P55 章节:5.2.5 展示/评审:当团队以用户故事的形式完成特定功能时,团队会定期展示工作产品。看过展示后,产品负责人接受或拒绝故事。 冲刺评审会议的结果是一份修订的产品待办列表,确定很可能进入下个冲刺的产品代办列表。