在某建设工程项目的地基开挖过程中,对于因气候原因造成的进度延后风险,项目经理采取了风险接受的策略。由于在施工期间下特大雨,工程不得不停工3天。项目经理应该怎么做?
During the foundation excavation of a construction project, the project manager adopts risk acceptance strategy for the delay risk caused by climate reasons. Due to the extremely heavy rain during the construction period, the project has to be suspended for 3 days. What should project manager do?
A.使用应急储备 To use emergency reserves
B.把项目工期延长3天 To extend the project duration by 3 days
C.要求保险公司赔偿 To make a claim to the insurer
D.与团队成员开会讨论处理方案 To meet and discuss with team members for handling solutions
参考答案:A
解析:知识点出处:PMBOK 6th 页码:P443 章节:11.5.2.4 接受风险接受是指承认威胁的存在,但不主动采取措施。接受策略又分为主动或被动方式。最常见的主动接受策略是建立应急储备。被动接受策略则不会主动采取行动。 最常见的主动接受策略是建立应急储备。