项目经理正在考虑项目风险和制约因素,然后组织了一次与高级员工召开的头脑风暴,了解当前流程,项目经理向部门经理讲述了业务影响相关问题,并审查了风险和制约的因素,在咨询信息技术部门的一名方案架构师的意见后,项目经理要求获得输入和评估。项目经理使用的是哪种工具和技术?
A project manager look at the project’s risk and constrains and then organizes a brainstorming session with senior staff to understand the current processes. The project manager speaks with department managers regarding business impacts ,and reviews risks and constraints. Consulting with a solution architect in the information technology department ,the project manager asks for inputs and assessments. What tool and technique is the project manager using?
A.风险登记册模板 Risk register template
B.专家判断 Expert judgment
C.组织过程资产 Organizational process assets
D.外部分析 External analysis
参考答案:B
解析:知识点出处:PMBOK 6th 页码:P414 章节:11.2.2.1 专家判断:应考虑了解类似项目或业务领域的个人或小组的专业意见。项目经理应该选择相关专家,邀请他们根据以往经验和专业知识来考虑单个项目风险的方方面面,以及整体项目风险的各种来源。 咨询专家后得出进一步的工作方向,是典型的专家判断。