“微信扫一扫”进入"可可试卷"微信小程序刷题
一个敏捷团队正在努力实现一个积极的发布目标。scrum master最近注意到,其中一位开发人员的表现下降了,而且她参加小组讨论的次数似乎减少了。scrum master应该做什么?
An agile team is working to meet an aggressive release goal. The scrum master has recently noticed that the performance of one of the developers has dropped and the developer seems to be participating less in group discussions. What should the scrum master do?
A.要求其余团队成员完成此开发人员的工作量 Request the rest of the team members to backfill the workload of the developer
B.在冲刺回顾会议上讨论开发人员的绩效问题 Discuss the developer's performance issues at the sprint retrospective meeting
C.私下与开发人员会面,并尝试确定激发他们动机的因素 Meet with the developer privately and try to determine what motivates them
D.寻找替代者,因为敏捷团队需要最好的人才 Look for a replacement because agile teams require the best talent available
参考答案:C
解析:知识点出处:敏捷实践指南 页码:P38 章节:4.3 仆人式领导:要善于激励项目人员,为他们提供所需的环境和支持,信任他们能够完成工作。 项目经理要激励成员,并提供支持。