在项目执行期间,项目经理发现在规划期间未考虑政府法规。经过详细分析后,项目经理解决了这个问题。若要阻止再次发生这个问题,项目经理应该做什么?
During project execution, the project manager found that government regulations were not considered during the planning period. After a detailed analysis, the project manager resolved the issue. What should the project manager do to prevent this problem from happening again?
A.将该过程记录在风险登记册中 Record this process in the risk register
B.在问题日志中记录该事项 Record this in the issue log
C.更新经验教训 Update lessons learned
D.向指导委员会通知解决方案 Inform the steering committee of the solution
参考答案:C
解析:知识点出处:PMBOK 6th 页码:P104 章节:4.4.3.1 经验教训登记册:经验教训登记册可以记录遇到的挑战、问题、意识到的风险和机会,或其他适用的内容。经验教训登记册在早期创建,在整个项目期间,它可以作为很多过程的输入,也可以作为输出而不断更新。 经验教训改善未来绩效。