你的上一个敏捷项目遭受了各种各样的延迟,比如陈述和验证需求、编写和测试代码、要求客户澄清需求和接收澄清之间的时间间隔。在即将到来的敏捷项目中,你希望应用一些精益敏捷实践来确保减少或完全消除时间浪费。在计划即将到来的项目时,你最好的行动方案是什么?
Your last agile project suffered from various delays, such as time passing between stating and verifying requirements, writing and testing code, and asking customers to clarify requirements and receiving clarifications. In your upcoming agile project, you want to apply some lean-agile practices to ensure that time waste reduced or entirely eliminated. What is your best course of action while planning your upcoming project?
A.制定并严格执行详细的项目管理计划 Develop and rigorously follow a detailed project management plan
B.使用根本原因分析技术查找过程中的瓶颈 Use the root cause analysis techniques to find bottlenecks in the process
C.创建自主团队并为他们提供所需的资源 Create a self-directed team and provide them with the resources they need
D.安排与客户的电话会议以明确要求 Schedule conference calls with the customer to clarify requirements
参考答案:C
解析:知识点出处:敏捷实践指南 页码:P9 章节:2.2 自组织团队最符合敏捷的价值观和原则