一个项目经理正在为一个建造定制工业冲压机床的项目制定质量管理计划。这台机器将由供应商生产的部件组装而成。为了确定质量成本,项目经理检查一致性和非一致性的成本。项目经理应该审查下列哪一项以确定一致性的成本?(选择四个)
A project manager is developing a quality management plan for a project to build a custom industrial stamping machine. The machine will be assembled from parts produced by vendors. To determine the cost of quality, the project manager examines the costs of conformance and nonconformance.Which of the following should the project manager review to determine the cost of conformance? (Choose four)


A.因零件或工艺缺陷而引起的保修费用 The cost of warranty claims due to defective parts or workmanship

B.与项目团队培训相关的成本 Costs associated with training of the project team

C.组装前与机器单个部件测试有关的费用 Expenses related to the testing of individual parts of the machine prior to assembly

D.因破坏性试验而引起的损失 Losses incurred as the result of destructive testing

E.由于产品故障而导致业务损失的经济价值 The economic value of lost business due to product failures

F.在生产过程中与部件检查相关的成本 Costs related to inspections of subassemblies during the manufacturing process


知识点:PMP新模考(二)


参考答案:BCDF


解析:知识点出处:PMBOK 6th
页码:P282章节:8.1.2.3质量成本:预防成本、评估成本、内部失败成本、外部失败成本。一致性成本的核心就是花钱规避失败。