一个没有敏捷方法经验的组织雇佣了一个敏捷教练来领导一个项目。该项目将使用看板开发项目可交付成果。下列哪项培训活动对项目的成功至关重要?(选择三个)
A scrum master has been hired to lead a project  for an organization that has no prior experience with agile methodologies. The project will use Scrumban for the development of project deliverables.Which of the following training activities will be critical for the success of the project? (Choose three)


A.与整个项目团队一起举办关于敏捷思维和原则的敏捷研讨会 Conducting an agile workshop on the agile mindset and principles with the entire project team

B.教授开发团队如何根据业务价值对项目待办事项排序 Teaching the development team how to prioritize the project backlog according to business value

C.向开发团队解释工作将如何通过看板,以及如何遵守在制品限制 Explaining to the development team how the work will flow through the Kanban board and how to follow WIP limits

D.确保产品负责人清楚地了解如何培养待定项 Ensuring that the product owner has a clear understanding of how to groom the backlog

E.对产品负责人进行日常scrum会议的最佳实践培训 Training the product owner on best practices for facilitating the daily scrum meetings

F.指导项目团队如何确保严格的变更控制过程的实施 Instructing the project team on how to ensure the implementation of a rigid change control process


知识点:PMP新模考(二)


参考答案:ACD


解析:知识点出处:敏捷实践指南页码:P82章节:6.6.3通过培训和指导发展人才。B应该PO来做;E是整个团队而非单纯PO;F错误。