项目已完成并获得客户批准,IT部门计划对项目进行不定期审计。项目经理应该怎么做?
The project has been completed and approved by the customer. The IT department plans to conduct an unscheduled audit on the project. What should the project manager do?
A.请求审查IT部门的质量保证政策 Request to review IT departments quality assurance policy
B.告知项目发起人IT审计不是质量管理计划的一部分 Inform the project sponsor that the IT audit is not part of the quality management plan
C.审查公司政策并通知涉及项目的干系人 Review the companys policies and notify the project stakeholders
D.允许审计,因为可以为项目提供更多价值 Allow auditing, because it can provide more value to the project
参考答案:D
解析:知识点出处:PMBOK 6th 页码:P294 章节:8.2.2.5 审计:识别良好及最佳实践;识别所有违规做法、差距及不足;分享良好实践;改进过程的执行,从而帮助团队提高生产效率;强调每次审计都应对组织经验教训知识库的积累做出贡献。 审计好处多多,应该对审计持有开放的态度。