当项目发起人找到Scrum主管,要求在当前的冲刺中立即开发一个新的、紧急的、潜在的复杂的强制性法规遵循相关的需求时,Scrum团队正处于冲刺的中途。发起人强调,如果需求没有实现,整个项目可能会被取消。Scrum主管的最佳回应是什么?
A scrum team is midway into a sprint when the project sponsor approaches the scrum master and requests that a new, urgent, and potentially complex mandatory compliance-related requirement should be developed immediately in the current sprint. The sponsor stresses that if the requirement is not implemented, the entire project may be canceled. What is the scrum master’s best response?


A.将要求添加到产品待办事项列表,并请求产品负责人在冲刺结束之后审查需求 Add the requirement to the product backlog and request the product owner to review the requirement after the sprint is over

B.与产品负责人讨论要求,让他们做出决定,包括冲刺取消 Discuss the requirement with the product owner, and let them make a decision, including sprint cancellation

C.提交变更请求以更新范围基准并将要求添加到需求可追溯性矩阵 Submit a change request to update the scope baseline and add the requirement to the requirement traceability matrix

D.将要求添加到当前冲刺待办事项列表,并指示团队立即开始处理该待办事项列表 Add the requirement to the current sprint backlog and direct the team to start working on it immediately


知识点:PMP新模考(二)


参考答案:B


解析:知识点出处:敏捷实践指南 页码:41 章节:4.3.2 产品负责人 Product Owner: 创建待办列表并排序、 确认工作优先顺序、 提供反馈、 指导开发方向。 是否变更,由PO决定。