一个敏捷团队正处于冲刺中,此时发起人要求项目经理停止当前冲刺中几个用户故事的工作。由于最近发布的一项新技术即将上市,发起人倾向于认为这些用户故事没有什么价值。项目经理应该做什么?
An agile team is in the middle of a sprint when the sponsor asks the project manager to stop work on several user stories in the current sprint. With a recent news announcement of new technology soon to hit the market, the sponsor is inclined to think that these user stories would be of little value. What should the project manager do?
A.从冲刺待办事项列表移除发起人指定的用户故事 Remove the user stories indicated by the sponsor from the sprint backlog
B.忽略发起人意见,并指示团队按原计划进行 Ignore the sponsor's input and instruct the team to proceed as originally planned
C.联系产品负责人,询问用户故事是否仍具有优先级 Contact the product owner and ask if the user stories are still a priority
D.进行市场调查以确认新技术的发布 Conduct market research to confirm the announcement of the new technology
参考答案:C
解析:知识点出处:敏捷实践指南 页码:41 章节:4.3.2 产品负责人 Product Owner :创建待办列表并排序、 确认工作优先顺序 、提供反馈、 指导开发方向。 优先级的问题, 应该听PO的。