在项目开展六个月后,项目经理了解到需要进行变更,而这需要增加批准的预算。项目经理应该做什么?
Six months after the project was launched,the project manager learned that changes were needed, which required an increase in the approved budget. What should the project manager do?
A.接受该变更,并通知发起人 Accept the change and notify the sponsor
B.开始变更请求过程 Initiate the change request progress
C.请求财务部门提供额外资金 Ask the finance department for additional funds
D.拒绝该变更,以保持项目正常运行 Reject the change to keep the project on track
参考答案:B
解析:知识点出处:PMBOK 6th 页码:P113 章节:4.6 变更流程:变更提出后,先分析影响,再提交含解决措施的变更请求给CCB。审批前,三步骤提出变更-分析影响-提交审批。