项目经理前往另一个国家执行最终可交付成果的上线过程,到达后,项目经理得知,由于任务计划在当地假日期间完成,关键资源将不可用,而延迟上线将使最终项目的交付处于危险之中。若要避免这个问题,项目经理应该在项目开始时完成哪一项工作?
The project manager travels to another country to perform the final deliverable on-line process. Upon arrival, the project manager learns that because the task is scheduled to be completed during the local holiday period, key resources will be unavailable, and the delayed on-line will make the final project delivery at risk.To avoid this problem, which task should the project manager complete at the beginning of the project?
A.创建一份团队日历并围绕该信息创建项目进度计划 Create a team calendar and create a project schedule around that information
B.要求所有团队,无论在哪个国家,均遵循总部的日历 Require all teams, regardless of country, to follow the headquarters calendar
C.制定加班预算以补偿在假期工作的资源 Develop an overtime budget to compensate for resources that work during the holidays
D.记录风险登记册中包含各个国家日历的影响 Record the effect of the national calendar in the risk register
参考答案:A
解析:知识点出处: PMBOK 6th 页码:P323 章节:9.2.1.2 资源日历: 资源日历识别了每种具体资源可用时的工作日、班次、正常营业的上下班时间、周末和公共假期。在规划活动期间,潜在的可用资源信息(如团队资源、设备和材料)用于估算资源可用性。资源日历还规定了在项目期间确定的团队和实物 资源何时可用、可用多久。