一个为期两年的项目完成了50%,进度绩效指数1.051和成本绩效指数为1.02。一个新的项目进入投资组合,被视为一个优先级并且高于当前的项目。因此,目前项目失去了三个关键资源。尽管资源紧张,但是高级主管仍然要求项目经理按时完成项目,并且按照预算且不会有额外的资源补给。 项目经理应该怎样做?
A two-year project is 50% complete has a schedule performance index of 1.051and a cost performance index of 1.02, A new project enters the portfolio and is deemed a higher priority than the current project. As a result, the current project loses three key resources. Despite tossing resources, the project manager is asked by senior management to complete the project on time and within budget without additional resources. What should do next?
A.执行资源平衡 executive resources balance
B.赶工 crashing
C.变更项目基准 change the project baseline
D.实施偏差分析 implements deviation analysis
参考答案:D
解析:知识点出处:PMBOK 6th 页码:P262 章节:7.4.2.2 偏差分析:可开展偏差分析,来识别成本基准与实际项目绩效之间的差异;然后可以实施进一步的分析,以判定偏离进度基准的原因和程度,并决定是否需要采取纠正或预防措施。 先进行偏差分析,再确认是否要采取纠正或预防措施。ABC都是措施。