“微信扫一扫”进入"可可试卷"微信小程序刷题

项目管理专业人士资格认证(PMP)题库(1459题)


在一个为期12个月的项目中,供应商通知项目经理所需的项目设备将被延迟,经过进一步调查后,项目经理得知该供应商在业绩表现方面口碑不佳。若要避免这个问题,项目经理应该事先做什么?
One month into a 12-month project,a vendor informs the project manager that required project equipment will be delayed.After further investigation,the project manager learns that this vendor has a reputation for under performing.What should the project manager have done to prevent this?


A.检查更新后的风险登记册和问题日志 Check the updated risk register and issue log

B.在供应商名单中添加备份供应商 Added a backup vendor to vendor list

C.在进度计划基准中包含应急缓冲 Include a contingency buffer in the schedule baseline

D.查看其它项目的经验教训文档 Reviewed the lessons learned documents from other projects


知识点:PMP新模考(二)


参考答案:D


解析:知识点出处:PMBOK 6th 页码:P484 章节:12.2.1.2 经验教训登记册:在项目早期获取的与实施采购有关的经验教训,可用于项目后期阶段,以提高本过程的效率。 实施采购之前,先看这家供应商之前的口碑,以避免问题。

进入考试题库