项目管理专业人士资格认证(PMP)题库(1459题)


一家公司正在几个国家部署一个新的解决方案,已包含安全审计作为每次部署的质量检查组成部分。第一次部署后进行的安全审计结果发现了违反安全的行为以及不合规问题。项目经理应该做什么?
A company is deploying a new solution in several countries and has included security audits as part of the quality check for each deployment. The security audit conducted after the first deployment found security violations and non-compliance issues. What should the project manager do?


A.组织团队研讨会以执行根本原因分析并定义纠正措施计划 Organize team workshops to perform root cause analysis and define corrective action plans

B.审查质量管理计划,以确认是否包含安全要求 Review the quality management plan to confirm that it includes safety requirements

C.与安全审计员协商降低已发现问题的重要性 Consult with a security auditor to reduce the importance of identified issues

D.验证质量要求与解决方案是否一致,并更新质量管理计划 Verify that the quality requirements and solutions are consistent and update the quality management plan


知识点:PMP新模考(二)


参考答案:A


解析:知识点出处: PMBOK 6th 页码:P296 章节:8.2.3.3 变更请求:如果管理质量过程期间出现了可能影响项目管理计划任何组成部分、项目文件或项目/产品管理过程的变更,项目经理应提交变更请求并遵循 4.6 节定义的实施整体变更控制过程。 安全问题与不合规问题必须纠正,否则项目不会成功。