在一个公路施工项中,最近出现了返工的情况,导致项目经理非常担心项目的不一致性成本。项目经理来寻求你的帮助。你能给他的最好的建议是?
In a road construction project, the rework that happened lately makes the project manager very concerned about the inconsistency cost of no-conformance. The project manager turns to you for help. What is the best advice you can offer?
A.重新进行规划质量管理过程 To re-plan the quality management process
B.加强质量控制 To strengthen the quality control
C.开展质量审计 To perform quality audit
D.开展标杆对照 To carry out benchmarking control
参考答案:C
解析:知识点出处: PMBOK 6th 页码:P295 章节:8.2.2.5 审计:采取后续措施纠正问题,可以降低质量成本,并提高发起人或客户对项目产品的接受度。 审计可以降低质量成本。