项目的混凝土供应商通知项目经理,材料将比预定时间晚三个星期交付。项目经理更新了进度计划并通知项目团队。在这种情况下,哪种合同类型承担的风险最小?
A project’s concrete supplier informs the project manager that the material will be delivered three weeks later than scheduled.The project manager update the schedule and notifies the project team. In this situation,what contract type carries the least amount of project risk ?
A.总价加激励费用合同(FPIF) Fixed price incentive fee(FPIF)
B.总价加经济价格调整合同(FPEPA) Fixed price with economic price adjustment(FPEPA)
C.工料合同(T&M) Time and material(T&M)
D.固定总价合同(FFP) Fixed total price contract(FFP)
参考答案:D
解析:知识点出处: PMBOK 6th 页码:P471 章节:12.1.1.6 总价合同:此类合同为既定产品、服务或成果的采购设定一个总价。这种合同应在已明确定义需求,且不会出现重大范围变更的情况下使用。 范围明确,要选择固定总价合同。