项目管理专业人士资格认证(PMP)题库(1459题)


项目经理正在创建一份文件,正式授权建筑改造项目。装修要求拆除石棉绝缘材料,因为它是一种已知致癌物。这种情况会如何影响目前正在进行的过程?
A project manager is in the process of creating a document that formally authorizes a building renovation project. The renovation requires the removal of asbestos insulation, which is a known carcinogen. How might this situation influence the process currently underway?


A.应急储备需要分配并记录在文件中 A contingency reserve needs to be assigned and recorded in the document

B.该文件需要包括对已识别的风险的详细的风险应对计划 The document needs to include a detailed risk response plan for this identified risk

C.该文件需要符合任何适用的政府和行业标准 The document needs to incorporate compliance with any applicable government and industry standards

D.移除石棉的详细时间表应包含在文件中 A detailed timeline for the removal of the asbestos should be included in the document


知识点:PMP新模考(二)


参考答案:C


解析:知识点出处:PMBOK 6th 页码:P78 章节:4.1.1.3 事业环境因素政府或行业标准法律法规要求和制约因素。 授权项目的文件指得是项目章程,ABD都不属于启动阶段。