由于内部需求,项目主题专家(SME)的职能经理要求项目发起人更新负责该地区的项目主题专家(SME),该SME对该项目十分关键,他的决定将对项目的进度计划产生严重风险。项目经理应该做什么?
Due to internal needs, the functional manager of the project subject matter expert (SME) asked the project sponsor to update the project subject matter expert (SME) in charge of the area. This SME is critical to the project, and his decision will pose a serious risk to the project schedule.What should the project manager do?
A.请求与项目发起人及职能经理开会 Request a meeting with the project sponsor and functional manager
B.释放该SME并更新项目进度计划 Release the SME and update the project schedule
C.与该SME交谈,请求其留在项目中 Talk to the SME and ask it to stay in the project
D.向项目发起人请求提供额外资金以聘请一位新SME Ask the project sponsor for additional funding to hire a new SME
参考答案:A
解析:知识点出处: PMBOK 6th 页码:P329 章节:9.3 获取资源的重要性:不能获得项目所需的资源时,可能会影响项目进度、预算、客户满意度、质量和风险;资源或人员能力不足会降低项目成功的概率,最坏的情况可能导致项目取消。 专家不可或缺,先考虑找职能经理协商