在最后一次迭代结束的前几天,团队通知项目经理,他们将无法完成两个工作包A和B,因为WBS不够完善。团队认为他们可能能够按时完成包A,但需要额外一周的时间来完成包B,后者的优先级更高。对项目经理来说,最好的行动方案是什么?
A few days before the end of the last iteration, the team informs the project manager that they will be unable to finish two work packages, A and B, because the WBS is insufficiently refined. The team thinks they might be able to complete package A on time but will need an additional week to complete package B which has a higher priority. What is the best course of action for the project manager?
A.扩展迭代长度以完成包A和B Extend the iteration length in order to finish both packages A and B
B.指示团队完成包B,因为它具有更高优先级 Instruct the team to complete package B since it has a higher priority
C.指示团队完成包A,因为它可以及时完成 Instruct the team to complete package A since it can be done on time
D.咨询产品负责人并做出相应的决定 Consult with the product owner and make a decision accordingly
参考答案:D
解析:知识点出处: 敏捷实践指南 页码:41 章节:4.3.2 产品负责人 Product Owner :创建待办列表并排序、 确认工作优先顺序 、提供反馈 、指导开发方向 。 产品负责人来确定需求的优先级。