你正在创建在你的公司部署一个新的ERP软件的时间表。该公司目前正在进行敏捷转型,因此决定迭代开发新的ERP。ERP的第一个版本应该在四个月内推出,你知道另一个全公司范围操作系统升级的项目计划在三个月内推出。随着升级项目影响你的进度,你应该评估以下哪一项以确定在推出前的迭代次数?
You are creating the schedule to deploy a new ERP software in your company. The company is currently undergoing an agile transformation, so it was decided to develop the new ERP iteratively. The first release of the ERP should be rolled out in four months, and you know that another project, a company-wide operating system upgrade, is scheduled in three months. With the upgrade project affecting your schedule, an impact on which of the following should you assess to determine the number of iterations until rollout?


A.发布规划 Release planning

B.产品路线图 Product roadmap

C.迭代待办事项列表 Iteration backlogs

D.项目章程 Project charter


知识点:PMP新模考(二)


参考答案:A


解析:知识点出处:PMBOK 6th 页码:P216 章节:6.5.2.8 敏捷发布规划基于项目路线图和产品发展愿景,提供了高度概括的发布进度时间轴(通常是 3 到 6个月)。同时,敏捷发布规划还确定了发布的迭代或冲刺次数,使产品负责人和团队能够决定需要开发的内容,并基于业务目标、依赖关系和障碍因素确定达到产品放行所需的时间。 敏捷发布规划确定了发布迭代次数或冲刺次数