政府已与一家供应商签订合同,为即将到来的选举开发一款计算选票的软件应用程序。需求得到了很好的定义,这样项目就可以按照传统方式进行管理。然而,由于过去类似应用程序的失败,政府希望供应商能够对可交付内容的适用性进行快速反馈。供应商的项目经理选择什么样的进度计划方法最好?
A vendor has been contracted by the government to develop a software application to count votes for the upcoming elections. The requirements are well defined so that the project can be managed traditionally. However, due to failures in similar applications in the past, the government wants the vendor to allow rapid feedback on the suitability of the deliverables. What scheduling approach is best for the vendor's project manager to select?
A.预测式 Predictive
B.传统式 Traditional
C.高效式 Elective
D.适应式 Adaptive
参考答案:D
解析:知识点出处:敏捷实践指南 页码:P18 章节:3.1 四种生命周期特征。 反复执行,频繁小规模交付,为敏捷型