在一个软件开发项目的规划阶段,公司被承诺如果比约定交付时间提前两个月交付产品,公司将获得一份奖励,产品开发的项目经理让编程人员在需求和设计完成之前开始代码编写。这种情况下,项目经理在应用哪项进度技术?
During the planning phase of a software development project, the company is offered an incentive to deliver the product two months earlier than the agreed upon delivery date. The project manager for the product development asks the programmer to start coding before the requirements and design are completed. Which scheduling technique is the project manager applying in this situation?


A.赶工 Crashing

B.快速执行 Fast implementation

C.快速跟进 Fast tracking

D.分阶段执行 Phased implementation


知识点:PMP新模考(二)


参考答案:C


解析:知识点出处:PMBOK 6th 页码:P228 章节:6.6.2.6 进度压缩采用进度压缩技术(见 6.5.2.6 节)使进度落后的项目活动赶上计划,可以对剩余工作使用快速跟进或赶工方法。 把任务并行属于快速跟进。