你领导着两个独立的团队在同一个项目上工作。可交付成果的性质要求一个团队采用预测法,而另一个团队使用Scrum。由于团队之间的依赖性和Scrum团队输出的可变性质,预测性团队需要用尽可能短的反馈循环来确认他们对Scrum团队活动的理解。你的最佳行动方案是什么?
You are leading two independent teams working on the same project. The nature of the deliverables requires that one team takes a predictive approach, while the other uses Scrum. Due to dependencies between the teams and the variable nature of the outputs from the Scrum team, the predictive team needs to confirm their understanding of the Scrum team's activities with the shortest feedback loop possible. What is your best course of action?
A.将项目回顾纳入项目进度计划 Include a project retrospective into the project schedule
B.要求Scrum团队使用信息发射源 Request that the Scrum team use information radiators
C.结合定期的客户反馈循环的使用 Incorporate the use of periodic customer feedback loops
D.让预测团队参加每日Scrum会议 Have the predictive team attend the daily scrum meetings
参考答案:D
解析:知识点出处:敏捷实践指南页码:P54章节:5.2.4为每日站会规定时间盒,不超出 15 分钟。团队以某种方式“过一下”看板或任务板,而团队中的任何人都可以主持站会。每天15分钟的站会能以最短的时间获得一手信息,比信息发射源更及时