下列哪个选项描述的是应急储备金?
Which of the following options describes contingency reserve?
A.为未计划的项目范围和成本变更而储备的预算 Budget reserved for unplanned changes to project scope and cost
B.为掩盖较差的业绩而储备的预算 Budget reserved for covering poor performance
C.为未计划但是可能由于风险登记册中登记风险成真而潜在要求的变更而储备的预算 Budget reserved for unplanned but potential required changes that can result from realized risks identified in the risk register
D.为支付批准变更所产生的超支费用而储备的预算 Budget reserved for covering cost overrun due to approved changes
参考答案:C
解析:知识点出处: PMBOK 6th 页码:P246 章节:7.2.3.1 应急储备: 成本估算包括对完成项目工作可能需要的成本、应对已识别风险的应急储备,以及应对计划外工作的管理储备的量化估算。 应急储备用于已知风险,管理储备用于未知风险