一家供应商称因为某项主要功能未包含在约定的范围内,所以未能实施。项目团队不认同这一说法,项目经理下一步应该做什么?
A supplier said that a major function could not be implemented because it was not included in the agreed scope. The project team did not agree with this statement. What should the project manager do next?
A.将该问题升级上报给项目发起人解决 Escalate the issue to the project sponsor for resolution
B.签发一份报价邀请书(RFQ),聘请新的供应商 Issue an invitation to quote (RFQ) and hire a new supplier
C.要求法律部门对供应商采取行动 Ask the legal department to take action on the supplier
D.审查采购管理计划和合同协议 Review the procurement management plan and contract agreement
参考答案:D
解析:知识点出处: PMBOK 6th 页码:P489 章节:12.2.3.2 协议:可包括(但不限于): • 采购工作说明书或主要的 可交付成果; • 进度计划、里程碑,或进度计划中规定的日期; • 绩效报告; • 定价和支付条款; • 检查、质量和验收标准; 范围有歧义, 查看合同中对可交付成果的定义