在迭代回顾会议上,团队回顾了上一次迭代的各种指标。度量标准包括速度、吞吐量和在制品(WIP)。团队成员分析数据并得出结论,他们的周期时间非常高,应该减少。这个团队向项目经理寻求建议。项目经理最好建议以下哪个选项?
At the iteration retrospective meeting, the team reviews the various metrics from the last iteration. The metrics include velocity, throughput, and work in progress (WIP). The team members analyze the data and conclude that their cycle time is very high and should be reduced. The team approaches the project manager for advice. Which of the following options is the best for the project manager to recommend?


A.减少WIP和吞吐量 Decrease WIP and throughput

B.提高WIP数量、生产速度和生产效率 Increase WIP, velocity, and throughout

C.增加WIP和生产能力 Increase WIP and throughput

D.减少WIP数量,提高生产能力 Decrease WIP and increase throughput


知识点:PMP新模考(二)


参考答案:D


解析:知识点出处: 敏捷实践指南 页码:P103 章节:A3.4 看板方法: 通过限制在制品将可以提高工作效率和质量。 通过WIP(在制品管理)来提高工作效率与质量。