随着项目进行,项目经理会收到干系人的抱怨,他们声称项目状态会议和电子邮件报告太少,无法让干系人了解项目的最新状态。项目经理审查沟通管理计划,并提交变更请求以修改报告状态的方式。项目经理最好在变更请求中包含以下哪项?
As the project progresses, the project manager gets complaints from stakeholders who say that project status meetings and email reports are too infrequent to keep the stakeholders up-to-date with the project's status. The project manager reviews the communications management plan and submits a change request to modify the way the status is reported. Which of the following is best for the project manager to include in the change request?


A.结合使用信息发射源 Incorporating the use of information radiators

B.终止分发电子邮件报告 Eliminating the distribution of email reports

C.在每日站会汇报项目状况 Reporting project status at the daily standups

D.将项目状态发送给更少的干系人 Sending project status to fewer stakeholders


知识点:PMP新模考(二)


参考答案:A


解析:知识点出处: 敏捷实践指南 页码:P152 章节:术语表 信息发射源:它是一种可见的实物展示其向组织内其他成员提供信息在不干扰团队的情况下即时实现知识共享。 信息发射源一般包括看板、燃尽图、燃起图、障碍日志等。 在敏捷项目中,使用可见的实物展示信息更透明化。 C每日站会不报告项目状态。