你正在预测管理项目的敏捷阶段的中途。公司CEO刚刚通知你们,由于疫情蔓延,所有非必要人员将被要求远程工作,包括你们的项目团队。然而,资源管理计划要求使用集中办公来增强沟通和协作。你的最佳行动方案是什么?
You are midway into an agile phase of a predictively managed project. You have just been notified by the company's CEO that, due to a growing pandemic, all non-essential personnel will be required to work remotely, including your project team. However, the resource management plan mandates the use of physical colocation to enhance communication and collaboration. What is your best course of action?
A.请求变更资源管理计划,以合并使用虚拟工具在远程环境中集中办公 Request a change to the resource management plan to incorporate the use of virtual tools to replicate colocation in a remote environment
B.检查虚拟团队成员的需求,调查替代方案,并实现虚拟团队成员参与的选项 Examine virtual team member needs, investigate alternatives, and implement options for virtual team member engagement
C.提交变更请求以更新项目管理计划,将项目管理方法从混合式转变成预测性 Submit a change request to update the project management plan to migrate the project management approach from hybrid to predictive
D.将项目暂停直到疫情结束,然后让小组回到现场工作,以遵守资源管理计划 Put the project on hold until the pandemic is over and then bring the team back on-site to comply with the resource management plan
参考答案:A
解析:知识点出处: PMBOK 6th 页码:P357 章节:9.6.3.2 如果控制资源过程出现变更请求,或者推荐的纠正措施 或预防措施影响了项目管理计划的任何组成部分或项目 文件,项目经理应提交变更请求。并通过实施整体变更 控制过程(见 4.6节)对变更请求进行审查和处理。 确定变更了,就提交变更,更改资源管理计划。