项目管理专业人士资格认证(PMP)题库(1459题)


项目已完成60%,此时一名项目干系人建议增加一个新事项,提高项目效益,为此,需要额外的资金。 项目经理应该怎么做?
The project has been completed 60%.At this point,a project stakeholder suggests adding a new item to improve the project efficiency. Therefore ,additional funds are required. What should the project manager do?


A.包含该新事项 To include this new item

B.请求变更控制委员会(CCB)的批准 To request for approval of the Change Control Board (CCB)

C.更新成本管理计划,反映额外的资金 To update the cost control plan to reflect additional funds

D.拒绝该请求 To reject the request


知识点:PMP新模考(二)


参考答案:B


解析:知识点出处:PMBOK 6th 页码:P113 章节:4.6 变更提出后,先分析影响,再提交含解决措施的变更请求给CCB。 审批前,三步骤提出变更-分析影响-提交审批