项目经理领导着一个由不同知识和经验水平的成员组成的项目团队。有些人是专家,有些人经验不足一年。项目进度得到了指导委员会的批准。项目经理应该做什么?
A project manager is leading a project team composed of members with varying levels of knowledge and experience. Some are experts and some have less than 1 year of experience. The project schedule was approved by the steering committee. What should the project manager do?


A.要求经验较少的成员完全按照经验丰富的成员的指示执行任务。 Ask the less-experienced members to perform tasks exactly as they are instructed by the experienced members.

B.要求每个有经验的成员成为一个经验较少的成员的导师。 Ask each experienced member to be the mentor to one of the less-experienced members.

C.要求经验丰富的成员审查所有由经验较少的成员完成的任务。 Ask the more experienced members to review all of the tasks performed by the less-experienced members.

D.要求资源经理用更有经验的团队成员替换经验较少的成员。 Ask the resource manager to replace the less-experienced members with more experienced team members.


知识点:PMP新模考(三)


参考答案:B


解析:最佳选项是B,“让每个经验丰富的成员成为一个经验不足的成员的导师。”这种方法可以让经验不足的会员从项目中有知识和经验的人那里获得指导和支持,并有助于建立团队士气,鼓励知识共享。其他选项可能会导致绩效不佳、动力下降和士气下降。