A项目小组已订立采购车辆和建筑服务的合同。在项目执行过程中,项目团队得知车辆供应商无法交付车辆。没有足够的时间在不耽误项目的情况下找到新的供应商。项目经理应该采取什么行动来采购车辆?
A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project. Which action should the project manager take to procure the vehicles?


A.要求技术团队修改需求,即使这需要额外的预算。 Ask the technical team to revise the requirements, even if it requires extra budget.

B.安排与客户的会议,要求额外的时间寻找新的供应商 Arrange a meeting with the client to request additional time to find a new supplier.

C.审查现有的服务合约,寻找协助采购车辆的方案。 Review the existing service contracts to find an option to help procure the vehicles.

D.从其他供应商采购车辆,并将变更报告给变更控制委员会。 Procure the vehicles from another supplier and report the change to the change control board (CCB) later.


知识点:PMP新模考(三)


参考答案:C


解析:选C,项目经理应审查现有服务合同,以找到帮助采购车辆的选项,这将有助于避免项目延误。如果现有合同中有允许替代采购或应急措施的条款,项目经理应探讨这些选项。选项D可能是解决方案之一,但是应该在C之后。在这种情况下,其他选项(如修改要求或要求客户提供额外时间)可能不可行或不实用。