某公司正在运用预测型方法开发范围管理计划中定义的一个特定组件。由于监管要求会定期变更,开发团队己请求运用敏捷方法。针对开发团队的请求,项目经理应做什么?A company is using a predictive approach for the development of a particular component as defined in the scope management plan.Due to regularly changing regulatory requirements,the development team has requested to utilize agile approaches.What should the project manager do about the development team's request?
A.上报额外财务资源请求。Escalate the request for additional financial resources.
B.对需要按所要求的方法予以应对的需求进行分析。Analyze the requirements that will need to be addressed under the requested method.
C.将该请求转交给项目管理办公室(PMO),并对组织过程资产作出修改。Forward the request to the project management office (PMO)to amend the organizational process assets.
D.请求项目发起人批准实施该新方法。Ask the project sponsor to obtain approval for implementation of the new approach.
参考答案:B
解析:《PMBOK》第6版113页,4.6-实施整体变更控制。项目实施所采用的开发方法(预测型、增量型、迭代型、适应型、混合型)在项目管理计划中做了预先定义。因此,在项目实施期间,如果对开发方法进行调整,需要通过实施整体变更控制流程,不能擅自变更,选项B正确。选项A,是否需要额外的财务资源投入,在变更控制过程进行评估和决策。选项C,如果影响到了基准,由CCB进行决策,而不是PMO。选项D,由谁决策,要查看变更管理计划。