项目经理正处于一个高度可见的项目的执行阶段,一个重要的里程碑将在三周后到期。项目经理发现供应商为此里程碑的交付将延迟五周。项目经理应该怎么做?The project manager is in the execution phase of a highly visible project with a major milestone due in three weeks. The project manager found that the supplier's delivery for this milestone would be delayed by five weeks. What should a project manager do?
A.不要在状态会议上报告这个问题Do not report this issue in a status meeting
B.与团队会面并集思广益并制定解决此问题的方法Meet with the team and brainstorm and develop a solution to this problem
C.停止向供应商付款,直到收到可交付成果Stop paying suppliers until deliverables are received
D.报告错过的里程碑的状态Report the status of missed milestones
参考答案:B
解析:解析:《PMBOK》第6版492页,12.3-控制采购。”供应商为此里程碑的交付将延迟五周“,对外的采购合作出现了问题,要研判延迟交付所带来的影响并进行干预,选项B正确。选项A,不报告这个问题,问题已然存在,做法不可取。选项C,项目的进度会受到供应商交付速度的影响,供应商不能按时交付,首先要考虑到项目会不会受到影响,而不是款项。选项D,里程碑尚未到期,还不是”错过“的状态。