项目经理签订了一份合同,领导一个供应商团队,执行全国性的系统实施项目。项目启动后,合同签订组织宣布对系统进行变更,因为另一个独立供应商团队完成了额外工作,这导致合同发生变化,项目经理应如何处理这些变化?
A project manager signs a contract to lead a team of vendors for a nationwide system implementation project. After initiation , the contracting organization announces changes to the system, as additional work was completed by another team of independent vendor.this resulted in variations to the contract. How should the project manager deal with these changes?


A.审查协议并为额外工作项开具发票 Review the agreements and invoices the additional work items

B.支持供应商团队根据初始合同实施这些变更 Support the vendor team implementing the changes as per the initial contract

C.与供应商合作,提供有关工作的专家指导和检查点 Work with the vendor to provide expert guidance and check points on the work

D.与该组织合作制定支持变更和升级上报流程的计划 Work with the organization to develop a plan that supports the change and escalation processes


知识点:PMP新模考(三)


参考答案:D


解析:解析:PMBOK(6)4.2 制定项目管理计划。项目经理签了合同,拿了个活,结果刚准备做,被组织的其他团队完成了一部分了,所以要更改合同范围。为了应对这种变化,项目经理应先做好支持变更以及上报的计划。 其他选项:A,直接开具发票不符合流程,B,已经有了变更不能按初始合同来做。C,合同变更阶段,还没有到具体的供应商工作执行。