项目经理如何制定项目管理计划,以确保项目持续交付预期效益?How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?
A.对每次发布进行集成测试。Perform integration testing of each release.
B.将整个项目团队纳入测试。Include the entire project team in testing.
C.向发起人澄清项目效益。Clarify project benefits with the sponsor.
D.确定各个工作产品的目标。Identify the goal of each work product.
参考答案:D
解析:制定管理计划时确保收益,要交付收益,就要全面评估所有产品的目标,要确定目标。