某大型水电厂开发项目正处于实施阶段,是运用混合型方法管理的。项目经理该做什么来确保在执行阶段完全符合质量要求?A project to develop a large hydropower plant is in the implementation phase and is managed using a hybrid approach.What should the project manager do to ensure full compliance of quality requirements during the execution phase?
A.规划质量管理。Plan quality management.
B.持续审查可交付成果的质量。Continually survey the quality of the deliverable.
C.分析质量要求。Analyze the quality requirements.
D.制定质量政策和程序。Set up quality policies and procedures.
参考答案:B
解析:问的是过程中,自然就是一个监控活动,只有B选项符合。