一位项目经理正在领导一个为一家贸易公司开发会计软件的项目。在交付成果的同时,政府将在未来6个月内更改间接税法规,从而确定了新的风险。这一风险将对项目成果产生重大影响。项目经理下一步应该怎么做?
A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact on the project outcomes. What should the project manager do next?
A.确定风险的影响,并确定不影响税务模块的结果的优先次序。 Determine the impact of the risk and prioritize outcomes that do not affect the tax module.
B.将间接税模块的开发推迟到税收法规生效后。 Delay developing the indirect tax module until the tax regulation comes into effect.
C.与专家一起评估风险的影响,并与客户一起确定进一步结果的优先次序。 Assess the impact of the risk with an expert and prioritize further outcomes with the client
D.分析风险的影响,与团队讨论,确定如何分离税务模块。 Analyze the impact of the risk and discuss with the team to determine how to separate the tax module.
参考答案:C
解析:识别到风险,1记录、2分析、3、规划应对、4实施。最佳选项是(C)与专家一起评估风险的影响并与客户一起确定进一步结果的优先级。这将确保项目成果符合不断变化的税收法规,并确保项目在规定的时间框架和预算内交付。项目经理可以让一位专家来了解风险对项目的影响,并与客户进行讨论,以确定结果的优先级,并确定减轻风险的最佳方式。选项D,分离税务模块不一定是解决风险的最佳解决方案。