项目管理专业人士资格认证(PMP)题库(1459题)


项目经理正准备启动一个新项目,其中的团队成员分布在不同的国家。项目经理正在使用沟通管理计划来吸引团队成员,并找到适合每个人的沟通方法。项目经理应该如何持续评估虚拟团队参与的有效性?
A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone. How should the project manager continually evaluate the effectiveness of the virtual team's engagement?


A.收集团队的反馈意见,讨论改善沟通的方案。 Collect feedback from the team to discuss alternatives to enhance the communication.

B.单独举行会议,与团队成员创造信任的环境。 Conduct individual meetings to create a trusting environment with team members.

C.定期召开面对面会议,讨论沟通议题。 Establish periodic face-to-face meetings and address the communication topic.

D.根据团队成员的偏好和可用性举行会议。 Hold meetings in accordance with the team members' preferences and availability.


知识点:PMP新模考(三)


参考答案:A


解析:题目中问的是“如何持续评估虚拟团队参与的有效性”,排除BD选项,与问题无关。在此题中团队成员分布在不同的国家,A优于C,选A。