项目管理专业人士资格认证(PMP)题库(1459题)


在一次迭代过程中,一个正在开发新产品的敏捷团队接到通知,一个重要的团队成员由于一些紧急的个人问题将离开项目几周。对于这个团队成员负责的活动,项目经理应该做些什么呢?
In the middle of iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues.  What should the project manager do regarding the activities that were the responsibility of this team member?


A.与团队就如何处理这种情况达成一致。 Reach an agreement with the team on how to handle the situation.

B.与采购团队联系,雇佣一名替代该团队成员的人。 Reach out to the procurement team to hire a substitute for the team member.

C.允许高级管理人员决定如何进行项目。 Allow senior management to decide how to proceed with the project.

D.说服团队成员在项目完成之前不要离开。 Convince the team member not to leave until the project is complete


知识点:PMP新模考(三)


参考答案:A


解析:选A,在敏捷项目中,团队是自组织的。项目经理应与团队合作,确定如何处理关键团队成员离开几周的情况。选项A是最好的选择,因为它涉及与团队就如何处理情况达成一致,这尊重团队的自主性和自组织性。