项目经理是跨职能敏捷团队中的一员。项目经理被分配了一个具有多个功能的软件项目,该项目将花费团队大约一年的时间来完成。首席执行官坚持认为,解决方案需要满足年底的业务目标,也就是6个月后的目标。项目经理应该做什么来使干系人的需求和期望一致?
A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6 months. What should the project manager do to align stakeholders' needs and expectations?
A.与干系人合作,创建优先待办事项列表事项并发布路线图。 Work with the stakeholders to create a prioritized backlog and release a roadmap.
B.将要求修改为可在6个月内完成的要求。 Modify the requirements to those that can be completed in 6 months.
C.实施快速跟进和赶工活动,在6个月内完成项目。 Implement fast-tracking and crashing activities to complete the project in 6 months.
D.在日常scrum会议中包括所有干系人,让他们了解情况。 Include all stakeholders in daily scrum meetings to keep them informed
参考答案:A
解析:项目经理应与干系人合作,创建优先待办事项列表事项并发布路线图,以协调干系人的需求和期望。这使项目经理能够理解业务目标,在6个月的期限内确定要交付的功能的优先级,并制定实现这些目标的计划。路线图有助于干系人了解项目的进展情况,优先处理的待办事项可以帮助团队专注于最重要的功能。因此,选项A是正确的答案。选项D不是最好的方法,因为在日常scrum会议中包括所有干系人可能不是必要的或有效的。