项目管理专业人士资格认证(PMP)题库(1459题)


一些开发人员在每日站会上列出了一份障碍因素清单,并要求项目负责人帮助确定它们的优先次序。有一些复杂的待办事项列表中的事项,一个新的初级测试人员已经发现了一些合规性缺陷。产品负责人和几个开发人员将离开项目团队,与测试和生产支持合作伙伴的合同将不再续签。项目负责人应该首先关注哪一个问题?
A few developers have identified a list of impediments at the daily standup and are asking for the project lead's assistance in prioritizing them.  There are a few complex backlog items, and a new junior tester has identified a few compliance defects.  The product owner and a couple of developers will be leaving the project team, and the contract with the test and production support partner will not be renewed. Which issue should the project lead focus on first?


A.开发新的生产支持合同。 Developing a new contract for production support.

B.找到一个新的产品负责人来确定产品待办事项列表的优先级。 Finding a new product owner to prioritize the product backlog.

C.会议讨论监管合规问题。 Regulatory compliance issues discussed in the meeting.

D.招聘、入职和培训新的开发人员。 Recruiting, on boarding, and training new developers.


知识点:PMP新模考(三)


参考答案:C


解析:选C,项目负责人应首先关注合规问题。如果不及时解决合规缺陷,可能会产生严重后果,如罚款、法律问题或对公司声誉的负面影响。这一问题需要优先处理,并尽快得到解决。之后,项目负责人可以解决其他问题。