发起人要求项目达到既定的质量标准。因此,发起人要求项目经理采取稳定的措施,以确保质量得到满足。项目经理应该做哪三件事?(选择三个)A sponsor requires that the established quality standards for the project be met. As a result, the sponsor asks the project manager for stable measures to ensure that the quality is met. Which three things should the project manager do?(Choose three)


A.分析经验教训,以确定质量标准中适当的测试指标。Analyze the lessons learned to determine appropriate testing metrics in quality standards.

B.在迭代规划中确定符合质量标准的验收标准。Identify in the iteration planning the acceptance criteria that meet quality standards.

C.根据质量标准,将绩效指标纳入经验证的可交付成果中。Incorporate performance metrics on the verified deliverables according to quality standards.

D.在回顾过程中确定符合质量标准的验收标准。Identify the acceptance criteria during the retrospective that meet the quality standards.

E.进行风险分析,以确定不符合质量标准的影响。Perform a risk analysis to determine the impact of not complying with quality standards.


知识点:PMP冲刺题


参考答案:ABC


解析:选项A正确,通过分析过去项目的经验教训,项目经理可以确定适当的测试指标,以更好地满足项目的质量标准。选项B正确,在项目迭代计划中明确验收标准,有助于确保项目交付成果在各个阶段都符合既定的质量标准。选项C正确,将绩效指标与交付成果相结合,可以帮助项目经理跟踪评估项目在实现质量标准方面的表现。选项D错误,验收标准应在项目迭代计划阶段确定。选项E错误,评估项目风险不能直接确保项目满足既定的质量。