一个最近成立的敏捷团队在一天工作12个小时来完成sprint承诺后筋疲力尽。在这种情况下,谁没有正确地履行自己的职责? A recently formed agile team is exhausted after working 12-hourdays to fulfil sprint commitments. Who has NOT properly performed their duties in this situation?
A.项目经理 Project manager
B.团队成员 Team members
C.产品负责人 Product owner
D.Scrum教练 Scrum master
参考答案:D
解析:Scrum Master的角色是确保团队的工作条件,包括工作量,是适当的和可持续的。