当项目发起人要求额外的可交付物时,项目完成了70%。项目经理首先应该做什么?A project is 70% complete when the project sponsor requests an additional deliverable. What should the project manager do first?
A.拒绝请求,因为太迟,导致主要范围蔓延。Reject the request as being too late and leading to major scope creep.
B.向变更控制委员会(CCB)提出请求,以便作出决定。Submit the request to the change control board (CCB) for a decision.
C.与项目发起人就可能的替代办法进行谈判。Negotiate with the project sponsor on the possible alternatives.
D.确定这项变更对项目各方面可能产生的影响。Determine the possible impact of this change on all aspects of the project.
参考答案:D
解析:变更题,走变更流程,首先分析影响,选D。